Saskatoon construction crews ahead of schedule

$
0
0

Work begins on the project planned for 22nd Street and Circle Drive South in Saskatoon. Trelle Kolojay/News Talk Radio.

By Trelle Kolojay

Construction crews in Saskatoon are a bit ahead of schedule because of Mother Nature’s cooperation.

“The sun’s been out and the weather’s been great, so we’ve been able to get a lot of work done so far. The crews have completed about 58 lane kilometres of the 196 lane kilometres that were due to be completed this year,” Celene Anger, director of construction and design with the City of Saskatoon, said.

To help them meet their goal, construction crews will be hard at work on... // Read Full Article